Train Information


Tunnel Ventilation Fans Activation Schedules

Tunnel Ventilation Fans (TVFs) are installed near certain MRT stations along the North-South and East-West to provide air movement in MRT tunnels. 

TVFs are used primarily for:
1. Maintenance works in the tunnels during non-revenue hours. These include works such as tunnel washing, rail welding and rail grinding.
2. Emergency situations when commuters are evacuated from the tunnel to the nearest station platform.

The powered ventilation is necessary for the health, safety and comfort of our workers in the tunnel as the TVFs remove elements such as smoke, heat and dust generated during the maintenance works. 
 
We have made every effort to minimise noise and any inconvenience caused to neighbouring residential and commercial areas. Please watch this space for the latest schedule.

From 28 July to 3 August 2025

 

1Tanjong Pagar - Outram Park28 July 20250100 - 0430 hrs
2Orchard - Somerset28 July 20250100 - 0430 hrs
3Tiong Bahru - Outram Park 29 July 20250100 - 0430 hrs
4Somerset29 July 20250100 - 0430 hrs
5Dhoby Ghaut - Marina Bay31 July 20250100 - 0430 hrs
6Redhill - Tiong Bahru31 July 20250100 - 0430 hrs
7Tanjong Pagar - Outram Park1 August 20250100 - 0430 hrs
8Novena1 August 20250100 - 0430 hrs
9Newton - Novena3 August 20250100 - 0430 hrs









NOTE: The maintenance schedule is accurate at the time of publication but is subject to change due to unforeseen circumstances such as weather condition, urgent track work for safety reasons, etc.